Ribbon Cutting Ends Lakeway Road Improvements

Dozens of people braved the cold and wind Tuesday morning in the Knecht Home Center parking lot to celebrate the completion of the eight-month Lakeway Road improvement project from 4-J Road to Douglas Highway / Highway 59. L he groundbreaking event drew attention to the Penny Power’s Voluntary 1% Tax Funding project.

Gillette Mayor Louise Carter-King addressed the crowd and shared her appreciation for the quality work of Project Contractor DRM, Inc., City Consulting Engineer HDR Engineering, and all the sub-contractors who played a role in the project, including the businesses and citizens that she touched on a daily basis.

“I couldn’t be happier to report that this important project was completed both on time AND on budget,” the mayor said.

Carter-King reminded attendees that DRM, Inc. said it would end by the first week of November and that on October 29, all orange barrels were removed from the roadway, all five lanes were reopened. and the 30 mph speed limit was reinstated.

“The success of a project of this magnitude would not have been possible without the work of so many people. Thank you to the many Lakeway companies and their customers who have been so patient and understanding throughout the construction season, ”said Carter-King. “Thanks to HDR, DRM and their many contractors including Powder River Construction, Keyhole Technologies, Western Services, G&G Landscaping, TJ Electric, AET and KLJ. “

— Advertising – The story continues below –

The $ 7.16 million project was funded with money raised through the optional one percent sales tax, known locally as Penny Power. The city uses its share of the tax for improving drainage, improving fishing lakes, improving sewage treatment facilities, parks and trails and streets, to name a few- a few.

“Thank you to the many City staff members from several departments who participated in the project. A special thank you to the water and wastewater staff who carried out nightly shutdowns to minimize the impact on homes and businesses, ”concluded the mayor.

Highlights of the Lakeway Road Improvement

  • Lining of the existing 24-inch intercepting sanitary sewer from 4-J Road to Highway 59
  • Full-width surface replaced, including new concrete pavement and sidewalks from Chemin 4-J to Highway 59
  • Install water taps and replace fire hydrants from Chemin 4-J to Autoroute 59
  • New Main from Powder River Avenue to midpoint of Lakeway Road
  • Existing 18-inch sanitary sewer line on Emerson Avenue from Sequoia Drive to Lakeway Road
  • The life of nearly a mile of sewer line has been extended with the installation of a new coating
  • Over 100 water supply fittings and valves have been replaced or installed
  • 5 sanitary sewer manholes were installed, each having a depth of more than 20 feet. (If stacked end to end, they would collectively be 15 feet taller than the downtown First Interstate building)

By the numbers

9 inches of concrete used on the pavement

— Advertising – The story continues below –

6 inches of base crushed under the pavement

18 inches of sand under crushed base

8,500 cubic yards of concrete placed

19,000 cubic yards of foundation material

$ 8,000,000 – Total cost of the project